Q87. What is the inspection interval for buried piping without cathodic protection, the soil resistivity is 6,500 ohm-cm?

 
 
 
 

Q88. The preheat zone shall extend beyond each edge of a pipe weld

 
 
 
 

Q89. The repair organization shall use welders and welding operators qualified in accordance with the code to which the piping was built or alternatively_____.

 
 
 
 

Q90. Rerating piping systems may be allowed only if the calculations are performed by

 
 
 
 

Q91. In lieu of the required heat treatment after welding, what may be used as an alternative?

 
 
 
 

Q92. All piping system repair and alteration welding shall be done in accordance with:

 
 
 
 

Q93. Which of the following applies to socket welds in piping systems?

 
 
 
 

Q94. 375″
0.190″
0.03 inches/year 5 Years
MAWP:

 
 
 
 

Q95. What is the maximum length allowed for individual slag trapped in a weld in a Severe Cyclic Conditions piping system?

 
 
 
 

Q96. Excessive cyclic stresses that are well below the static yield strength of the material result in.

 
 
 
 

Q97. What is the design thickness of NPS 2 ½, SA106 Gr.B pipe that operates at 25 psi / 200°F

 
 
 
 

Q98. Erosion of the piping system usually occurs at:

 
 
 
 

Q99. The liquid penetrant examination method is an effective means for detecting.

 
 
 
 

Q100. A qualified welder may seal weld a threaded joint if_______.

 
 
 
 

Q101. What does the acronym MAWP refer to?

 
 
 
 

Q102. What is the minimum lifting power of an AC electromagnetic yoke used in magnetic particle inspection?

 
 
 
 

Q103. Each piece of magnetizing equipment shall be calibrated

 
 
 
 

Q104. All proposed methods of design, execution, materials, welding procedures, examination and testing must be approved by the.

 
 
 
 

Q105. Piping subject to CUI includes piping insulated for personnel protection, especially:

 
 
 
 

Q106. The downstream limit of the injection point circuit is the second change in flow direction past the injection point or:

 
 
 
 